Notes
Slide Show
Outline
1
 
2
Presentation Outline
  • Study Process
  • Recommendations
  • Why a new Middle School?
  • Next Steps
  • Proposed Project Timeline


3
Study Process
  • Schools Studies
    • Esten Elementary School
    • Jefferson Elementary School
    • Memorial Park Elementary School
    • Rogers Middle School
    • Rockland High School
  • Design Team Investigated Existing Conditions
    • Site
    • Building
    • Structure
    • Plumbing, Fire protection, HVAC, Electrical
    • Technology
    • Hazardous Materials
    • MSBA Rating (1-4)


4
Study Process
  • Educational Programs Developed
    • Administrators and Focus Group Meetings
    • N.E.S.D.E.C. Enrollment Projections
    • Grade Reorganization
      • K-4
      • 5-8
      • 9-12
    • Educational Specifications
  • Design Options Study
    • Multiple Options
      • The Cost to Maintain the Facilities
      • Additions/Renovations
      • New Construction
5
Recommendations
  • Build New Middle School behind existing building and raze old school building
  • Grade configuration
    • Grades 5 thru 8, or
    • Grades 6 thru 8 with a kindergarten center
  • Estimated cost in 2006 dollars
    • $37.5 million
    • 32 – 36 months construction
  • Target date - occupy fall 2011
6
Why a new Middle School?
  • Building a New 5-8 Middle School Rockland Achieves:
    • An 800 student capacity building
    • A School building designed to be a middle school
    • Available classroom space in the elementary school
    • Important community resource
7
Why a new Middle School?
  • Rogers Middle School Has Greatest Needs
    • Built 1928, Last Renovated 1976
    • Multiple Building Systems Needs
    • 4 ½ stories of Educational Space
    • Inhibits Modern Day Middle School Education
    • Current Educational Capacity of 375 students
    • Today’s Enrollment 630 students
    • MSBA rating of 3 out of 4; (4 being the worst)

8
Why a new Middle School?
  • Rogers Middle School Existing Capacity – 24 classrooms available
      • 15 classrooms @ 25 Students/CR=375 Students
      • 22 of 24 classrooms are smaller than 750 sqft.
      • There are no science rooms in excess of 720 sqft..




9
Why a new Middle School?
  • Educational Specifications
    • Rogers Middle School
      • 800 Grade 5 – 8 Students
      • (8) Teams = (2) 100 student teams/grade
      • 28 Math, English, Social Studies, Language Classrooms
      •   8 Science Classrooms with 4 prep rooms
      • 36 Total Classrooms
      • And…
10
Why a new Middle School?
      • Language Lab
      • Art, Band and Chorus
      • Family and Consumer Science
      • Computer Labs(4)
      • Library/Media Center
      • Gymnasium and Fitness Room
      • 500 Seat Auditorium
      • Special Education
      • Administration
      • Teacher and Support
      • Community Access Areas

11
Why a new Middle School?
  • New Middle School $37,426,475  32 Months
  • Additions/ Renovations to Existing Middle School $37,486,555  36 Months



  • Convert High School to A Middle School $52,476,780  48 Months
  • Add the cost of a new high school $42,875,000  32 Months
    •                                                         Total   $95,351,780


  • Combine the High School and Middle School $74,342,655



  • *The Projected Cost of Maintaining the Middle School  $13,121,767
    • Note: This cost has historically Not been reimbursable.


  • Project Costs are 2006 Dollars


12
Why a new Middle School?
      • New High School
      • 150,000 sf
      • $43 Million
      • 32-36 months to construct
      • Minimal School Disruption

13
 
14
 
15
 
16
 
17
 
18
Next Steps
  • Preliminary Schematic Design
    • Investigations
      • Site Survey
      • Geotechnical Analysis
      • Ground Water Study
      • Environmental Study
      • Traffic Study
      • Meet with abutters/neighborhood
      • Grant research and application writing
    • Develop The Educational Program
    • Develop The Design
    • Develop The Project Costs
    • Meet Regularly With The Building Committee
    • Meet With Town Boards, Departments and Officials
    • Conduct Community Forums
    • Discuss Project With MSBA
    • Report to Spring 2007 Town Meeting

19
Proposed Project Timeline
  • Spring 2006 - Feasibility Study
  • May 2006 - Town Meeting Report
  • *Secure Preliminary Design Funds
  • Summer 2006 - Preliminary Schematic Design
  • Spring 2007 - Town Meeting Report
  • *Secure Design Funds
  • July 2007 - MSBA Submission
  • Summer 2007 - Develop The Design
  • Spring 2008 - Town Meeting Report
  • *Secure Construction Funds
  • Summer 2008 - Commence Construction
  • Spring 2011 - Complete Construction
  • Summer 2011 - Demolish Existing Rogers Middle School
  • Fall 2011 - Occupy New Middle School